Edinburgh Tram Inquiry
The Edinburgh Tram inquiry is a public inquiry that is being held in Edinburgh to establish why the Edinburgh Trams project incurred delays, cost more than originally budgeted and delivered significantly less than was projected.
Timetable
No time frame has been set for how long the inquiry will take.[1]
On 5 June 2014, First Minister Alex Salmond announced a non-statutory public inquiry.[2] On 12 June 2014 Scottish Parliament were told that the inquiry would be headed by the former Lord Advocate, Andrew Hardie, Baron Hardie.[3] The Scottish Government subsequently announced on 7 November 2014 that the inquiry was to be upgraded to a statutory inquiry to ensure that key personnel would provide evidence.[4]
The first preliminary hearing took place on 6 October 2015.[1] It had been set back by a few weeks after Lord Hardie had a short unexpected stay in hospital.[5]
Anticipating some complexity around legal representation of the parties involved, Lord Hardie asked core participants to consider what conflicts of interest might exist and provide written responses to the inquiry by 27 November.[6]
Terms of Reference
The terms of reference for the inquiry are as follows:[7]
- To inquire into the delivery of the Edinburgh Trams project (“the project”), from proposals for the project emerging to its completion, including the procurement and contract preparation, its governance, project management and delivery structures, and oversight of the relevant contracts, in order to establish why the project incurred delays, cost considerably more than originally budgeted for and delivered significantly less than was projected through reductions in scope.
- To examine the consequences of the failure to deliver the project in the time, within the budget and to the extent projected.
- To otherwise review the circumstances surrounding the project as necessary, in order to report to the Scottish Ministers making recommendations as to how major tram and light rail infrastructure projects of a similar nature might avoid such failures in future.
The inquiry team is based in Edinburgh's Waverley Gate building, the capital's former General Post Office.[8]
Core participants
At the first preliminary hearing on 6 October 2015, Lord Hardie revealed that the parties who had applied for and been granted core participant status were: Bilfinger Construction UK, Carillion Utility Services, Edinburgh City Council, DLA Piper Scotland, Parsons Brinckerhoff, Scottish Ministers and Siemens.[1]
The city council had decided not to revive its former arms-length transport firm Transport Initiatives Edinburgh (Tie), therefore the former company could not be designated a core participant.[1]
Evidence
It was initially estimated that the inquiry might examine more than two million digital files and 200 boxes of documents as evidence.[9]
The hearings are due to make use of large screens, to display documents as they are referred to during the proceedings.[6]
Cost
In August 2015, Edinburgh City Council announced that they expected to spend up to £2 million participating in the inquiry.[10] The council spending would include the costs of legal assistance that would be provided to former councillors and staff.[10]
By July 2016, the inquiry itself had cost £3.7m, £1.822m of this being staffing costs, and £716,000 being legal fees.[11]
References
- 1 2 3 4 "Edinburgh tram inquiry: Six million documents to be examined". BBC News. 6 October 2015.
- ↑ "Edinburgh tram inquiry announced". BBC News. 5 June 2014. Retrieved 14 December 2014.
- ↑ "Lord Hardie to chair inquiry into Edinburgh trams fiasco". BBC News. 12 June 2014. Retrieved 14 December 2014.
- ↑ "Edinburgh Tram Inquiry" (Press release). Scottish Government. 7 November 2014. Retrieved 28 March 2015.
- ↑ Grant, Alistair (17 August 2015). "Tram inquiry hearing postponed as judge in hospital". Edinburgh Evening News. Retrieved 11 October 2015.
- 1 2 Dalton, Alastair (8 October 2015). "The truth will out in Edinburgh tram inquiry". The Scotsman. Retrieved 11 October 2015.
- ↑ "First Minister appoints judge for Edinburgh Trams Inquiry" (Press release). Scottish Government. 12 June 2014. Retrieved 14 December 2014.
- ↑ Miller, David (11 December 2014). "Edinburgh tram inquiry: Key figures refused to co-operate". BBC News. Retrieved 14 December 2014.
- ↑ Gourtsoyannis, Paris (11 December 2014). "Edinburgh trams inquiry 'needs public help'". Edinburgh Evening News. Retrieved 14 December 2014.
- 1 2 "Edinburgh city council to spend up to £2m on tram inquiry". BBC News. 13 August 2015.
- ↑ "Cost of inquiry into Edinburgh tram project hits £3.7m". BBC News. 21 July 2016.