Twin Sails Bridge
The Twin Sails Bridge (also known as The second harbour crossing) is a double leaved bascule bridge in Poole, Dorset, England. The bridge provides a second road link from Poole town centre to Hamworthy. The intention is that the bridge will allow development of four major sites, two in the town centre and two in Hamworthy, including the old power station which was closed in 1988.[1]
Location
The bridge spans the Backwater Channel which links Holes Bay with Poole Harbour. The bridge and approach roads are connected to the junction of West Quay Road in the East and to urban feeder roads in the West.
Design
The new bridge is intended to operate alongside the existing Poole Bridge with one of the bridges always open for vehicular traffic (except during closures for maintenance or in a marine emergency), the intention is that variable-message signs will direct traffic to the open bridge.[2] The bridge comprises a 10.8-metre (35 ft) wide carriageway with two vehicular lanes and two separate cycle lanes.[3] Additionally two 2.5-metre (8 ft) wide footpaths are provided which cantilever from the bridge. The bridge is constructed in five spans, with a total length of roughly 139 metres (456 ft). The approaches comprise two 27-metre (89 ft) spans, the centre lifting span consists of two triangular leaves that span 23.4 metres (77 ft) between the main bearings to provide a clear channel of 19 metres (62 ft) when open.[3] To permit the passage of boats through the navigation channel, the lift spans were planned to pivot to 88 degrees[4] powered by two hydraulic rams which operate up to 15 times per day[5] and take two minutes to fully open.[6] Two 55-metre (180 ft) high masts are fitted to the lifting leaves, the top two metres illuminated with white LED lights. [7] Four 7-metre (23 ft) high pillars housing the barriers, lights, speakers and traffic controls which link the bridge with the control room are located on the two fixed spans adjacent to the lifting section.
Hochtief (UK) Construction was awarded the £18.5 million contract for the construction of the bridge. The contract for the supply of around 900 tonnes of steel was awarded to Cleveland Bridge UK and Gifford UK (Ramboll) working with Wilkinson Eyre Architects are the lead design consultants. Metamont Ltd installed the marine grade stainless steel balustrade including the variable colour DMX lighting.[8]
History
Plans for a new bridge date to the 1980s, with the second lifting bridge concept being suggested in 2000 after a fixed bridge crossing Holes Bay and linking with the A31 was cancelled by the government in 1998. The council submitted detailed plans to Department for Transport in 2004 and following a public inquiry in 2005,[9] the £37 million[1] Twin Sails bridge project was given approval in 2006/7 but construction was initially delayed due to a stalemate between the council and the land owners.[10] After negotiations were settled in August 2009, there was a further delay in the allocation of the £14.14 million government grant which was finally agreed in March 2010.[11]
Construction began in May 2010 with completion and opening planned for late February 2012.[12] problems with the road surface caused the bridge to remain closed although the opening ceremony and visit by HRH The Princess Royal went ahead in early March 2012.[13] The bridge opened to traffic on 4 April 2012 after the road surface had been relaid, the first motor vehicle crossing at 9.38AM.[14] Problems with the bridge operation continued in the summer of 2012 with delays caused through the barrier operation and lifting mechanism as well as continuing defects in the road surface.[15]
References
- 1 2 Serck, Linda (4 February 2011). "Twin Sails Bridge divides opinion in Poole". BBC News. Retrieved 6 February 2012.
- ↑ "Twin Sails Bridge – On Time And on Budget | Poole". Pooleconservatives.org. 6 December 2012. Retrieved 8 February 2012.
- 1 2 "Twin Sails Bridge". Ramboll. Retrieved 16 December 2012.
- ↑ "Twin Sails Bridge". Road Traffic Technology. 15 June 2011. Retrieved 8 February 2012.
- ↑ "Twin Sails – Poole's bridge for the future" (PDF). Borough of Poole. Retrieved 8 February 2012.
- ↑ "Twin Sails Bridge rises to the challenge". Daily Echo. 15 October 2011. Retrieved 8 February 2012.
- ↑ "Poole's Twin Sails Bridge set for opening". Daily Echo. 3 February 2012. Retrieved 12 February 2012.
- ↑ "Twin Sails Bridge". Road Traffic Technology. 15 June 2011. Retrieved 5 February 2012.
- ↑ "Inquiry into town bridge". BBC News. 27 September 2005. Retrieved 5 February 2012.
- ↑ "Twin bridge is given the go-ahead". BBC News. 11 August 2006. Retrieved 5 February 2012.
- ↑ "Twin Sails – 30-year history" (PDF). Borough of Poole. 27 January 2011. Retrieved 12 February 2012.
- ↑ "Go ahead for Poole's Twin Sails Bridge". Daily Echo. 13 March 2010. Retrieved 5 February 2012.
- ↑ Henderson, Diana (21 March 2012). "Twin Sails bridge: no solution yet as asphalt removed from road surface". Bournemouth Echo. Retrieved 21 March 2012.
- ↑ Henderson, Diana (4 April 2012). "At last: Poole's Twin Sails bridge is to open to traffic". Bournemouth Echo. Retrieved 4 April 2012.
- ↑ Codd, Joanna (12 July 2012). "Council demands contractors fix Twin Sails Bridge after series of shutdowns". Bournemouth Echo. Retrieved 27 July 2012.
External links
Coordinates: 50°42′55″N 1°59′35″W / 50.715282°N 1.992932°W